Project Updates Week of 5/18/2020

UCNSB's contractor LMR is continuing Sanitary Sewer Rehabiliation work on beachside between Florida Ave. and Sapphire Rd, specifically on Sapphire Rd., N. Atlantic Ave. and Pine St. this week.

In addition, UCNSB's contractor Force Enterprises will begin excavating and well pointing at the intersection of Andrews St. and S. Riverside Dr.  This intersection will be closed all this week, per City Commission approval, and there will be an archeologist present if needed.  There is both pipe and manhole work at this location.