Sanitary Sewer Rehabilitative Lining Project

Schedule for the week of 1/27/2020: 

Monday – Tuesday:  Lining Pipe on 16th Ave. & 19th Ave. on beachside

Wednesday – Thursday:  Lining Pipe on Downing St.

Friday:  Lining Pipe on Live Oak St. at Andrews St. (near the hospital)

Status Update (chronological): 

Sanitary Sewer Rehabilitation Project