Sewer Pipe Rehabilitation Project Update 7/8/2020

UC's contractor, LMR, will continue to line the sanitary sewer pipe between Due East and Florida Avenue on the beachside.

This includes lining pipe in the rear lot easement between Crawford Ave. and Condict Dr. Traffic on North Peninsula Ave. will be detoured starting at 6pm, as needed.

This Thursday, 7/10/2020, LMR start lining manholes along Live Oak St., just east of the hospital.  This will not affect hospital traffic.

Further, LMR is in the process of cleaning and televising the sewer mains in the Venezia Neighborhood, Quay Assisi, Via Amalfi, Via Benevento, Via Capri and Via Duomo.  Pipe lining in Venezia will commence shortly thereafter.

Questions? please contact Dana Hale at 386-424-3037.

 

Status Update (chronological): 

Sewer Pipe Lining Project Update 7/8/2020