Week of January 20, 2020 Schedule for Sanitary Sewer Rehabilitation Project

Updated: January 21, 2020 - 8:00am

LMR will be working on 16th, 19th and 20th Avenues on Beachside this week. The UC's contractor, LMR Construction, Inc. will begin with cleaning the gravity sanitary sewer system, and once completed, will start the relining phase. There are no road closures anticipated; a lane shift or lane closure...Read more

Canal Street at US 1 Detour

Updated: January 15, 2020 - 8:22am

Please be aware if you are coming to our main office building at 200 Canal: Beginning Monday, Jan. 20 through Thursday, Jan. 24, Canal Street, just east of U.S. 1, will be closed from 10 pm- 5 am. The closure is needed to prepare the roadway for a traffic shift, and for construction activities...Read more

Holiday Schedule for Sewer System Improvements

Updated: December 11, 2019 - 10:38am

UC Contractor LMR will continue lining the sewer pipe along 2nd St. & 3rd St. this week (Dec 9-13) LMR will also line the manholes between 1st St. & 8th St., and clean & televise pipes between Wayne Ave. & 1st St. They will conduct very minimal work the week of Christmas and New...Read more

Turnbull Bay Road Water Main Extension

Updated: November 25, 2019 - 2:45pm

Our Water Resources crews have completed the installation of a water main extension on Turnbull Bay Road. Currently, the new service line is undergoing pressure testing. Once that is complete, the project is turned over to the Volusia County Department of Health to give the green light to place in...Read more

Fire Hydrant Inspection and Flow Testing

Updated: July 29, 2019 - 3:22pm

In conjunction with the CIty of New Smyrna Beach Fire Department, the UC and our contractor R&M Solutions will be inspecting, testing, cleaning, and painting fire hydrants throughout the city. We are starting the project today, 7/29/19, on the beachside north of Flagler Avenue, then moving to...Read more