Projects

Closure of Canal Street from Sams to Riverside

Updated: May 23, 2019 - 2:34pm

A detour will be in place on Canal Street between Sams Avenue and Riverside Drive on May 29 and 30 to allow the UC contractor to restore the pavers on the east end of Canal Street where the water main break took place last month. Please follow all directional signage around the work.Read more

FDOT U.S. 1 @ Canal Street Improvement Project

Updated: May 17, 2019 - 8:41am

The contractor, in coordination with UC staff, has completed the preparation work needed to begin replacing the water line on the west side of U.S. 1 on either side of Canal Street. Over the next two weeks, the contractor will be removing the old water pipe. There will be no disruption to any water...Read more

Manhole Rehabilitation

Updated: May 2, 2019 - 2:16pm

On Tuesday, May 7, starting about 8 pm, UC contractors J&H Waterstop will be performing manhole rehabiliation on 3rd Avenue in the eastbound travel lane at Saxon Drive. This will require lane closures, so please watch for alternate traffic patterns.Read more

Gravity Sanitary Sewer Rehabilitation Project

Updated: May 2, 2019 - 2:10pm

UCNSB contractors J&H Waterstop will perform gravity sanitary pipe lining on Columbus Avenue from Canova Drive to the river on Monday, May 6 from 7 am to approximately 7 pm. The work will require a lane closure; please watch for alternate traffic patterns.Read more

Gravity Sewer Rehabilitation

Updated: April 24, 2019 - 10:52am

Overnight Thursday, April 25, J&H Waterstop is scheduled to line the sewer main under Cedar Dunes Drive. Traffic will be altered on Saxon Drive, just south of 27th Avenue, to allow for the work to be performed. The project hours are expected to be 8 pm 4/25 to 5:30 am Friday, 4/26. If there are...Read more

Lift Station #11 on Riverside Drive Project

Updated: April 15, 2019 - 12:46pm

UPDATE as of 4/15/2019: The start-up of the new LS#11 on Riverside Drive will take place tomorrow, April 16. Riverside Drive is anticipated to be reopened by the end of the month. UPDATE as of 4/3/2019: PBWN has been rescinded. UPDATE as of 4/1/2019: During the course of work on this project today...Read more