Projects

Barracuda Bridge Utility Replacement Project

Updated: May 24, 2022 - 3:15pm

UC Project Manager: Dana Hale Contractor: Y-COM Start Date: December 2021 Projected Completion: August 2022 Project Area: Work extends along Quay Assisi, North Causeway and South Riverside Drive Project Impacts: T his project encompasses improvements to the infrastructure for three utilities -...Read more

Line 17 Electric Distribution Re-Build Project

Updated: April 5, 2022 - 4:32pm

UC Project Manager : Jameson Parker Contractor: Pike Construction Projected Start Date: March 2022 Projected Completion: May 2022 Project Size: Turnbull Bay Road from Pioneer Trail to Airport Substation, East of Sunset. Project Impact: This Modernization Roadmap initiative will improve electric...Read more

Reuse Reservoir Expansion and Pump Station Replacement

Updated: March 29, 2022 - 2:08pm

Project Highlights Video Update March 15: The tie-in between the existing pond and the pond expansion happened this morning, with excavators removing the berm between the two. Work continues on the new pump station. UC Project Manager: Darren Phegley Contractor: Carr & Collier, Inc. Start Date...Read more

Annual Gravity Sanitary Sewer Rehabilitation Project

Updated: March 29, 2022 - 1:43pm

Project Highlights Video UC Project Manager: Dana Hale Contractor: BLD Services, LLC/LMR Construction, Inc. Projected Start/Completion Date: Annual, ongoing project, projected to continue until 2024 Project Size: This project encompasses our entire service area. As of April 1, 2022, contractors are...Read more
Bio coming soon

Glencoe Well Rehab

Updated: February 3, 2022 - 1:12pm

Project Name: Rehabilitation of Glencoe Well Sites No. 2 and No. 3 UC Project Manager : Darren Phegley Contractor: McMahan Construction Co., Inc. Start Date: January 2022 Projected Completion: August 2022 Project Impact: This $1.1 million project will upgrade two, 64-year old potable drinking water...Read more